Worcestershire Parkway Rail Station

Published Monday, 31st December 2018

Latest Updates on the development of Worcestershire Parkway Rail Station

25 October 2018

Worcestershire Parkway

 

First look inside Worcestershire Parkway Rail Station

Work on the new Worcestershire Parkway Rail Station is progressing well with external steelworks and glazing nearly finished.

We have produced footage that shows the very first look inside the building, which is still under construction, and also aerial views which show the sheer scale of the project.

With the construction of the station building nearing completion, you can really get a sense of the enormity of this infrastructure project that is set to transform rail travel to and from the county.

Later this month work starts to install the 3 platforms, each being built in sections onsite but away from the track and then fitted into place. It will take nearly 70 sections to build each of the 265 metre long platforms.

Following installation of the platforms, work will then concentrate early in the new year on paving the car park and the landscaping and planting around the site whilst the internal elements of the station building continue to take shape.

12 October 2018

The roundabout on the B4084, near to where we are constructing the new Worcestershire Parkway Train Station, is now fully open to traffic,  ahead of schedule, and temporary traffic lights have been removed. Hear Jon Fraser from our highways team give an update on this video:

26 September 2018

Good news for commuters, residents and businesses who use the B4084 near the Worcestershire Parkway Station site.

The major highway works on the new roundabout are ahead of schedule so the night closures planned for this week are now no longer needed.

Temporary traffic lights will remain in place between the two railway bridges whilst the minor outstanding works are finished. Once complete, the temporary lights will be removed to allow two way traffic to operate through the new roundabout.

1 September 2018

Work on the new station is progressing well and the last phase of works on the highway outside the station entrance are due to be completed later this month.

Our contractor has to fully close the B4084 overnight between the two railway bridges commencing on Saturday 15th September for potentially just over three weeks in order to fully construct parts of the carriageway, surface the whole carriageway and carry out "signing and lining".

During the first week, the closure will be between 7pm and 6:30am as blocks of 11 hours are needed to complete full-depth construction of the carriageway; however, from Saturday 22nd September, the closures will be from 9pm until 6am.

Our contractors will use their best endeavours to complete the work earlier if possible.

Access to Woodbury Lane and Mucknall Farm Lane from/to the north will be unaffected.

A diversion will be signposted via the A4440/A44/B4084 for traffic broadly travelling in a northwest (Worcester) to southeast (Pershore/Evesham) direction and vice versa.

10 July 2018

Artist's impression July 2018

We invited the media to the Worcestershire Parkway Station construction to site today (10 July 2018) for update on progress and a closer look at the steel structure taking shape.

Once complete, the station, which is a key part of our plan to improve rail travel to and from the county, will track the way for more frequent and quicker trains to London and Birmingham.

Rail passenger volumes on Worcestershire routes are set to increase by up to 97% in the next 25 years, according to industry forecasts, and the Council is getting the county 'rail travel ready'.

The improvements already made at Worcester Foregate Street, Malvern Link and more recently Bromsgrove Station, mean these stations are now better equipped to deal with the predicted increase in passenger numbers. Along with the Kidderminster Station redevelopment and Worcestershire Parkway completing next year, rail travel to and from the county will soon be easier than it has been for the last 40 years.

For the full story visit Progress at Worcestershire Parkway Pushes Ahead.

June 2018

School pupils

School pupils from Worcestershire have been learning about what it takes to design and build a new railway station.

Year 7 youngsters from St Barnabas C of E First & Middle School in Drakes Broughton became 'engineers for the day' by looking at the challenges in designing Worcestershire Parkway Station.

Worcestershire County Council and the Engineering Director, Samantha Uren, from SLC Rail, who are managing the scheme on the Council's behalf, first visited the school last autumn to talk to pupils about civil engineering and other professions involved in the construction industry.

With Worcestershire Parkway Station on their doorstep, it was the perfect opportunity to talk to pupils about engineering in action. More recently, pupils also enjoyed a visit to the site where, their classroom learning was brought to life on a real life construction site.

For the full story visit Building a passion for engineering – the future generation.