Bewdley Public Realm Improvements and Air Quality Management
Area Scheme
As part of the third Worcestershire Local Transport Plan (LTP3),
improvements to Bewdley have been prioritised.
- As a result, the street lighting in Load Street has already
been upgraded and works to renew the footways in the same area are
about to start on 28 January 2013, for approximately 8 weeks
- The footways and kerbs will be renewed between the Angel PH and
George Hotel on the northside and between No. 1 and No. 15 HSBC
Bank on the southside. The new paving will be Tegula blocks, to
match the existing paving on the Severn side
- At the same time, there will be some Bridge repairs undertaken
(programmed to start w/c 28 January 2013, for approximately two
weeks). These works are to replace the bridge parapet at Beale's
corner. The works will be done under one-way traffic lights.
You can receive regular updates as and when they occur during
the delivery of the scheme by following us on Twitter: